Illinois is staring down a requirement for roughly 37 gigawatts of new generating resources and capacity purchases by 2035, a figure that underscores just how dramatically electricity demand is expected to grow across the state.
Data centres sit at the centre of that demand surge, with a newly released state planning document identifying them as the primary driver of rising electricity consumption and calling for direct policy intervention.
The Integrated Resource Plan report, published on November 16 alongside a separate draft Mitigation Plan, recommends that Illinois examine options to incentivise or require new data centres to reduce consumption during the highest-load hours each year.
Regulators are also considering rules that would compel new facilities to supply their own clean generation, storage, or capacity resources, or face mandatory flexible-operation requirements if they do not.
The twin documents were prepared under two separate pieces of legislation: the Climate and Equitable Jobs Act and the Clean and Reliable Grid Affordability Act, drawing in both the Illinois Power Agency and the Illinois Environmental Protection Agency.
Underlying both reports is a finding that Illinois currently faces a meaningful risk of generating capacity falling short of reliable demand, a gap that has forced planners to confront difficult trade-offs between emissions targets and grid stability.
To manage that shortfall in the near term, the draft Mitigation Plan proposes pushing back emissions-reduction deadlines for eligible gas- and oil-fired units operating within the PJM and MISO regions from 2030 to May 31, 2033, though coal plants are explicitly excluded from any such relief.
Any deadline extension would require formal authorisation from the Illinois Commerce Commission, and the plan stresses that the next IRP cycle should reassess whether continued operation of those units remains warranted beyond that date.
Every scenario across the IRP’s 22 modelled cases selected more four-hour battery storage than the state’s existing three-gigawatt statutory target, with the central projection pointing to approximately 12 GW of such batteries needed by 2035.
The future of Illinois’ nuclear fleet also features prominently, with the IRP recommending a review of the Carbon Mitigation Credit programme and an evaluation of output uprates at existing plants to determine whether additional state support is necessary.
Gas-fired capacity, whether sourced within Illinois or purchased from neighbouring states, is expected to remain a significant reliability backstop for the foreseeable future, and the report recommends studying the costs and feasibility of converting coal plants to gas or repurposing their sites entirely.
Stakeholders now have until January 15, 2027, to submit comments on the draft Mitigation Plan, after which the IPA and Illinois EPA will incorporate feedback and file a final version with the ICC for approval.
The ICC has separately opened a formal review of the IRP report under Docket No. 26-0824, with state agencies and intervenors expected to present detailed recommendations throughout the process and a final order anticipated by November 2027.