Alexey Gubarev: Europe’s Island States Need Power Before They Can Host the AI Boom

Data centers used 23% of Ireland's metered electricity last year, up from 5% in 2015, the Central Statistics Office says. This July, Malta and Cyprus each set a new record for peak demand.

Limassol-based entrepreneur and investor Alexey Gubarev, one of the founders of Cyprus’s TechIsland, argues that Europe’s smaller island states can win a real share of AI infrastructure, but only if they plan the power first and the data centres second.

Ireland is the EU’s clearest warning, and also its proof that an island can do this. According to the CSO, data centres consumed 7,663 GWh in 2025, or 23% of all metered electricity, after growing by 10% in a single year. Everyone else on the Irish grid grew by about 2%. That growth brought serious investment and jobs to a country at the edge of the continent. AI and cloud companies will happily go to an island if the island can give them power.

Ireland also shows what happens when the grid falls behind. Last December the Commission for Regulation of Utilities set new rules for connecting data centres. Large new sites now have to bring their own generation or storage, and within six years of being switched on they must cover 80% of their annual demand with new renewable power produced in Ireland. I think those conditions are sensible. They came, though, after a decade in which the industry’s share of the grid went from one in twenty to almost a quarter. Malta and Cyprus run much smaller systems, so the same mistake would arrive faster and cost more to undo.

Two islands at different points on the same road

Malta’s peak demand reached 741 MW this July, almost 12% above the record set in 2023, according to Enemalta. Cyprus hit 1,372 MW on 23 July, the highest figure its transmission system operator has ever recorded. Neither number includes a single large AI facility. Power is expensive too. Eurostat figures for the second half of 2025 put Ireland and Cyprus first and second for business electricity prices in the EU, at around 25 and 24 cents per kilowatt-hour.

The two islands are connected to the rest of Europe in very different ways. Malta has had a cable to Sicily since 2015 and is close to finishing a second one, a 122 km, 225 MW link to Ragusa costing about €297 million. The European Investment Bank signed €100 million of financing for it in April, and by October 92% of the land cable on the Sicilian side was in the ground.

Cyprus has no link at all yet. On 20 October the chairman of the energy regulator CERA told parliament that completion of the Great Sea Interconnector had moved back a year, to 1 January 2031, and that the estimated cost of €1.9 billion might not be enough. The project carries a €657 million EU grant, the largest the bloc has ever given to an electricity interconnection.

I don’t say any of this to rank one island above the other. Malta has spent a decade building the kind of redundancy Cyprus still lacks, while Cyprus has more land and a lot of sun to work with. They face the same arithmetic from different starting points.

How much a small grid can take

In April, researchers at Frederick University in Nicosia estimated that the Cypriot grid could take data centres of up to about 100 MW of IT load without major reinforcement. A facility of that size would equal almost 9% of the country’s installed generating capacity and use around 1,139 GWh of electricity a year.

I read that figure two ways. Cyprus has room for a few mid-sized facilities, which is more than many people assume. It also means one or two badly planned projects could swallow the whole margin, and every household and hotel would feel it in August.

I’ve worked in hosting and infrastructure since 2005, in several countries and on very different grids. In my experience the first question about any new site isn’t the tax rate or the rent. It’s how much power you can get, and what happens on the day the supply fails. Small island systems give less comfortable answers to all of that, so the planning has to be more careful.

Where islands fit in Europe’s AI map

Malta and Cyprus won’t host the giant clusters used to train frontier models, and they shouldn’t try. The realistic opportunity is facilities of tens of megawatts serving banks, shipping firms, public services and the growing number of companies that want their data processed inside the EU, close to their customers in southern Europe and the Eastern Mediterranean.

Brussels is moving in that direction. The Commission’s proposed Cloud and AI Development Act aims to triple the EU’s data centre capacity within five to seven years and to speed up permits in designated data centre acceleration zones. For a small state, that framework is only useful if the zones are drawn where the grid can actually carry the load.

What I would do first

Tie every data centre permit to a specific grid capacity, and publish a simple map of where that capacity exists. Investors would rather know the limit today than discover it in year three.

Treat data centres as part of the energy system. The Frederick study points out that large, steady demand could absorb surplus solar and wind and reduce curtailment, and coastal sites with seawater cooling could cut cooling energy by 10% to 15%. Ireland now asks for on-site generation or storage. An island with peaks every summer has even more reason to ask operators to bring batteries with them.

Compare notes across the water. Both islands run small systems, depend on one or two cables and see their peaks in the same heatwaves. That’s part of why I care about the work at TechIsland, where I sit on the board. Industry associations in Cyprus and Malta can share what they learn about demand and permits, and take a joint view to Brussels on how acceleration zones should work for island grids.

Ireland got the investment first and wrote the rules later. Malta and Cyprus still have time to do it the other way round.

Alexey Gubarev is a Cyprus-based entrepreneur, investor and collector. He co-founded Servers.com and Palta and is among the founders of TechIsland. Based in Limassol, he is also known by the spellings Aleksey Gubarev and Aleksej Gubarev. His retro car museum, located in Bishkek’s former Western Bus Station, is due to open in 2027. More at gubarev.com.